Series 8700 / 8800 Unitized Curtain Wall Assembly Instructions - Volume 5

Note:
Only silicone sealants which have been
developed and tested specifically for
structural glazing applications should
be used for glazing purposes.

Apply structural silicone

sealant into the void and

tool the joint to fill the

void completely.

Figure 106

Section 26 - Assembly and Glazing - SSG Vent at Fixed Horizontal

15. Apply structural silicone sealant into the void between the glass and mullion per the sealant manufacturer’s application instructions. See additional notes, and

figures below for sealant application and tooling instructions. A 90 degree nozzle may be required at the head and sill sash due to the fin bar at those
locations.

16. Immediately tool the sealant joint after application to insure the joint is completely filled with sealant on all four sides of each piece of glazing. Make sure no

air bubbles or voids are present in the sealant joint. See Figure 110.

17. Insert the HS32 setting blocks between the sill sash fin and glazing at quarter points or as directed per the final approved shop drawings. See Figure 104 on

page 55.

Insert HS32
setting block.

Apply structural silicone
sealant into the void.

Tool the joint to fill

the void completely.

Structural
Silicone Sealant

Structural

Silicone Sealant

Figure 107

Figure 108 - Head (Sill Similar)

Figure 109 - Jamb

Figure 110