Am series boilers and water heaters – AERCO AM Series Boiler User Manual User Manual

Page 77

Advertising
background image

AM Series Boilers and Water Heaters

CHAPTER 3 – INSTALLATION

OMM-0100_0B

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

Page 77 of 156

GF-146

Ph.: 800-526-0288

PRI - 07/14/14

3.16.5.19 Vertical Vent and Air Roof Termination Preparation

Prepare for installation of vent and air termination into a roof as follows:

Vertical Vent and Air Roof Termination Preparation

1. Air pipe penetration: cut a hole for the air pipe, sizing the air pipe hole as close as desired to

the air pipe outside diameter.

2. Vent pipe penetration:

a) Cut a hole for the vent pipe. For either combustible or noncombustible construction, size

the vent pipe hole with at least a 1/2 inch clearance around the vent pipe outer diameter;

b) Insert a galvanized metal thimble in the vent pipe hole.

3. Space the air and vent holes to provide the minimum spacing shown in Figure 3-37 and

listed in Section 3.16.5.18.

4. Follow all local codes for isolation of vent pipe when passing through floors, ceilings, and

roofs.

5. Provide flashing and sealing boots sized for the vent pipe and air pipe.

3.16.5.20 Installing Vertical Vent and Air Roof Terminations

Install vent and air terminations into a roof as follows:

Installing Vertical Vent and Air Roof Terminations

1. Prepare the vent termination and the air termination elbow (Figure 3-37) by inserting bird

screens.

2. The air piping must terminate in a down-turned 180° return bend as shown in Figure 3-37.

Locate the air inlet pipe no further than 2 feet from the center of the vent pipe. This
placement avoids recirculation of flue products into the combustion air stream.

3. Maintain the required dimensions of the finished termination piping as shown in Figure 3-37.

4. Do not extend exposed vent pipe outside of building more than shown in Figure 3-37.

Condensate could freeze and block vent pipe.

Advertising