22 vertical termination – concentric vent, 24 multi-venting vertical terminations, Am series boilers and water heaters – AERCO AM Series Boiler User Manual User Manual

Page 79

Advertising
background image

AM Series Boilers and Water Heaters

CHAPTER 3 – INSTALLATION

OMM-0100_0B

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

Page 79 of 156

GF-146

Ph.: 800-526-0288

PRI - 07/14/14

3.16.5.22 Vertical Termination – Concentric Vent

Both combustion air and vent pipes must attach to the termination. The termination must
terminate outside the structure and must be installed as shown in Figure 3-39.

3.16.5.23 Determining Location of Vertical Concentric Vent Termination

Locate the vertical concentric vent/air terminations using the following guidelines:

1. The total length of piping for vent or air must not exceed the limits given in the Section

3.16.3.

2. The concentric terminal must terminate at least 3 feet above the highest place in which the

vent penetrates the roof and at least 2 feet above any part of a building within 10 horizontal
feet.

3. Locate termination so it is not likely to be damaged by foreign objects, such as stones or

balls, or subject to buildup of leaves or sediment.

Figure 3-39:

Concentric Vertical Terminations

3.16.5.24 Multi-Venting Vertical Terminations

When two (2) or more direct vent appliances are vented near each other, each appliance must
be individually vented.

Advertising