MAINTENANCE

7-6

7.8 SHUTTING THE BOILER DOWN FOR
AN EXTENDED PERIOD OF TIME

If the boiler is to be tak en out of s ervice f or an

extended period of time (one year or more), the

following instructions must be followed.

1. Set ON/OFF switch on the front panel to the

OFF

pos ition to s hut d own th e bo iler’s

operating controls.

2. Disconnect AC power from the unit.
3. Close th e water s upply a nd r eturn v alves to

isolate boiler.

4. Close external gas supply valve.
5. Open relief valve to vent water pressure.

7.9 PLACING THE BOILER BACK IN
SERVICE AFTER A PROLONGED
SHUTDOWN

After a pr olonged shutdown (one year or more),

the following procedures must be followed:

1. Review installation requirements included in

Chapter 2.

2. Inspect a ll piping an d c onnections to the

unit.

3. Inspect exhaust vent, air duct (if applicable).

4. Perform initial startup per Chapter 4.

5. Perform s afety de vice t esting and the

scheduled m aintenance pr ocedures per

Chapters 6 and 7 of this manual.