Diag.16

d. Insert T-818-B-6 temperature sensor (40), take off sleeve (38) on E-201-C-9 combination

electrode (37), then insert E-201-C-9 combination electrode (37), put feeding tube (2) into the
bottom of solution bottle (1) all according to diagram 16.

Diag.17


e. While the meter is doing titration, if you need to change solution, the beaker should be taken

apart and assembled. Shown as diagram 17, loosen the screws (11) first, raise the whole
beaker system higher and turn to the position according to diagram 17, then turn the screws
(11) tight, hold the beaker (13) with hand, loosen the big nut (55), take out beaker (13), pour
solution out of the beaker (13), wash it for several times. Take notice: stirring drop (14)

must be cleaned as well. Fill the beaker (13) with measured solution. Take notice: stirring

drop (14) must be put at the bottom of the beaker (13). Install the beaker (13) to the
position, tighten the big nut (55) and loosen the screws (11), move the beaker system down
to make the beaker (13) touch the surface of the stirrer (15). The beaker should be put in the
middle of the stirrer (15). Finally turn screws (11) tight.