7 constructing a nudam network, 8 termination bus, 8• introduction – ADLINK ND-6520 User Manual

Page 12: Terminator connection

Advertising
background image

8

Introduction

1.7 Constructing a NuDAM Network

Go through the following steps, the user can construct a NuDAM network easily.

1. Setup a ND-6520 or ND-6530.

2. Connect the host computer with the ND-6520 or ND-6530.

3. Setup one or more ND-6510 if necessary.

4. Connect the ND-6510 to extend to RS-485 bus if necessary.

5. Install the NuDAM utility software or ND-6530 driver from disk.

6. Initialize the brand-new NuDAM modules.

7. Add the new NuDAM modules into RS-485 network.

Refer to chapter 2 and chapter 4 for executing step 1 and 2. Refer to chapter 3
for executing step 3, 4 and for understanding the time to install ND-6510. The
knowledge about the software for operating the NuDAM is in chapter 6. For
executing the step 6 and step 7, please refer to the install procedures of each
module and chapter 6.

1.8 Termination

Bus

In order to avoid signal reflections on the bus, each bus segment has to be
blanked off at its physical beginning and at its end with the characteristic
impedance. An termination resister ( Rt) is intalled for this purpose. The Rt value
- 120

Ω ± 2% is recommended, and the detailed connection of Rt can be referred

from the “Terminator Connection” diagram below.

Terminator Connection

Host

Data+

Data-

120 ohms

Data+

Data-

120 ohm s

Advertising