Installing the base module, 5installation, 2 installing the base module – Pilz PSSu E S 2DO 2-T User Manual

Page 21

Advertising
background image

Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Germany
Telephone: +49 711 3409-0, Telefax: +49 711 3409-133, E-Mail: [email protected]

5-3

5.2

Installing the base module

5

Installation

5.2

Installing the base module

5200

Installing the base module

5-

][Montage Basismodul

Prerequisite:

The head module must be installed.

If the head module does not have an integrated power supply, a sup-

ply voltage module must be installed to the right of the head module.

Please note:

For mechanical reasons it is not possible to mix base modules with

screw terminals and base modules with cage clamp terminals.

All contacts should be protected from contamination.

The mechanics of the base modules are designed for 50 plug in/out

cycles.

Procedure:

We recommend that you wire up the base modules before inserting

the electronic modules.

Slot the groove on the base module on to the mounting rail from be-

low [1].

Push the base module back [2] until you hear it lock into position.

On the mounting rail, slide the base module to the left until you hear

the two lateral mounting hooks on the adjacent module lock into po-

sition [3].

Schematic representation:

[2]

[1]

[3]

Advertising