Multiple Installations

In a multiple installation various types of

commercial refrigerating equipment are connected

to the same condensing unit.
The MAR can be one of the refrigeration units

connected to a multiple-use condensing unit or

rack. Hand shut-off valves on both liquid and

suction line is recommended for these

installations. One to be placed on the liquid line

and the other on suction line to isolate MAR SPLIT

unit when necessary.
Suction and Liquid line access valves must be

installed in the MAR circuit to evacuate its system.
In many multiple installations check valves are put

in the suction line of the coldest evaporator to

prevent warmer higher pressure low-side vapor

from moving into the colder evaporator during the

off periods.
The MAR liquid line connection must NOT be

connected downstream of any other unit’s liquid

line solenoid valve to insure that the MAR receives

refrigerant when it is required.

Installation of MAR SPLIT in multiple system

should be done in the following order.
1. Put MAR SPLIT unit in place.
See Location & Leveling.
2. Install valves and controls.
3. Install tubing.
See Refrigerant piping connections.
4. Make water piping connections.
See Plumbing.
5. Make electrical connections
See Electrical connections.
6. Check for leaks.
See Leak Test.
7. Dehydrate (evacuate) installation.
See Evacuation / Charging.
8. Start unit.
See Operational Check-out.