6 Commissioning the Automatic Switch Box

1. Check the following requirements:

– The Automatic Switch Box is installed properly.
– All cables are correctly and completely connected.
– All cables are tightly enclosed by the membrane at the bottom of the Automatic Switch Box.
– All cables in the Automatic Switch Box are trapped on the cable support rail provided for

that purpose.

– The base panels on the base of the Automatic Switch Box are attached.

2. Switch on the circuit breaker in the Automatic Switch Box.
3. Lock Automatic Switch Box with the switch cabinet key.
4. Attach the included sticker (hazard warning for consumer load system) in an clearly visible

position in or on the distribution to which the Sunny Backup-System is connected.
The sticker calls attention to the Sunny Backup-System and is intended to ensure that, if any work
needs to be carried out which requires disconnection, the Sunny Backup-System is also switched
off.

☑ The Automatic Switch Box is now ready for operation.