4 placing the pump out of operation, 5 reconnecting the pump – Moog RKP-II User Manual

Page 60

Advertising
background image

Placing the Pump out of Operation

7 Operation

52 User Manual RKP-II (CA53461-001; Version 2, January 2010) © 2010 Moog GmbH

7.4 Placing the Pump out of Operation

Placing the Pump out of
Operation

Pre-Conditions:

• The drive motor has been switched of and is secured from being switched

back on.

• Machine / equipment is at zero pressure and idle.

• Pump has cooled down.

Procedure:

1. Close the fittings on the suction and pressure side.

2. Completely drain the pump through the leakage oil port.

3. Depending on what is required:

- Remove the pump:

Ö Chap. "9.1 Demounting the Pump", Page 55

- Storing the Pump:

Ö Chap. "5.3 Storing the Pump", Page 31

7.5 Reconnecting the Pump

Reconnecting the Pump

Pre-Conditions:

• If the pump was stored: Measures were carried out that were necessary

because of the duration of storage.

Ö Tab. 6, Page 31

• Pump is installed.

Ö Chap. "6 Mounting", Page 33

Procedure:

1. Carry out all steps applicable for the initial set-up of the pump.

Ö Chap. "7.1 Initial Pump Set-Up", Page 43

DANGER

Risk of injury and property damage as a result of blows or
impact!
Unexpected and uncontrolled movement of the machine /
equipment may lead to severe injury or property damage.

• Only trained personnel should be allowed to remove the

pump.

• Have the equipment manufacturer or operator assure that

no uncontrolled signals are being transmitted to the pump.

• Make sure that the drive motor cannot start up.

WARNING

Risk of injury and poisoning by dangerous operating fluid!
Leaking operating fluid may lead to severe personal injury and
property damage.

• Only trained personnel should be allowed to place the

pump out of operation.

Advertising