Jumper configuration instructions, Ferrite ring installation, Figure 17 – Speed Queen Drying Tumblers none User Manual

Page 45

Advertising
background image

Electrical Requirements

43

70256801

© Copyright, Alliance Laundry Systems LLC – DO NOT COPY or TRANSMIT

Jumper Configuration Instructions

OPL Micro Control Models Only

Changing the transformer configuration jumper is

required if any of the following apply:

You have 208 Volt service and are connecting a

gas or steam model rated for 208 or 240 Volt.

You have 415 Volt service and are connecting a

gas or steam model rated for 380 or 415 Volt.

To configure your 208 or 240 Volt tumbler for

208 Volt operation, you must remove the 240 Volt

configuration jumper located in the contactor box and

replace it with the 208 Volt jumper supplied with the

information packet. This must be done prior to

supplying power to the machine. Failure to install

proper configuration jumper may result in damage to

sensitive electronic controls and may void warranty.
To configure your 380 or 415 Volt tumbler for

415 Volt operation, you must remove the 380 Volt

configuration jumper located in the contractor box and

replace it with the 415 Volt jumper supplied with the

information packet. This must be done prior to

supplying power to machine. Failure to install proper

configuration jumper may result in damage to

sensitive electronic controls and may void warranty.

Ferrite Ring Installation

Gas and Steam OPL Micro Control Models Only

The ferrite ring provided in the literature packet must

be installed over the power leads during connection of

electrical service. The ferrite protects the sensitive

electronic controls from destructive electrical

disturbances which may be present on power lines to

the machine. Failure to properly install the ferrite ring

may result in damage to the electronic controls and

will void control warranty.
To install:

1. Immediately after connection of power leads and

before applying power to machine, locate each of

the incoming service leads including ground.

2. Snap the ferrite ring closed over all the service

leads inside of the contactor box as shown. It is

important that the ferrite ring be installed inside

the contactor box as shown. Do not install the

ferrite outside of the box or other area. Make sure

that service leads are in the center of the ferrite

before closing the ring so as not to pinch or

damage leads.

Figure 17

T225S

1

Ferrite Ring

2

Contactor Box

3

Jumper

1

2

3

Advertising