External Maintenance Bypass Switch Configurations
The External Maintenance Bypass Switch has three configuration options:

• External maintenance bypass installed with interlock option
• External maintenance bypass installed without interlock option
• Not installed

Regardless of how the configuration is set, if the auxiliary contacts are open, the user is unable to

issue a retransfer command through the manual transfer / retransfer screen.
If the option is installed and the auxiliary contact status is read as switch is in the Bypass or Mainte-

nance position, the “critical load shutdown” message reads “UPS off”.

Multiple Battery Cabinets

The Npower system offers an option allowing for the installation of more than two battery cabinets.

The option consists of a Multiple Battery Breaker (MBB) board that mounts on the control door and

an Input Contact Isolator (ICI) board that mounts in the option area (See the Multiple Battery

Breaker Option in the options manual.)
The ICI board allows the Npower system to sense multiple battery cabinets, and the MBB board

allows the UPS to support multiple battery cabinets by supplying power to the UVR coil of additional

battery cabinets.
To access the screen for setting the number of battery cabinets in the system, navigate from the

MAIN MENU to CONFIGURATION to SYSTEM SETTINGS, page 3. Select NUMBER OF BAT-

TERY CABINETS to bring up the following password-protected screen.

Figure 29 Set number of battery cabinets screen

Set the number of battery cabinets by changing the number in the highlighted box. Pressing SELECT

will save this information and return Operator to the System Settings Screen.

Table 4

External maintenance switch configuration options

External

Maintenance Switch

Options

Option Auxiliary Contact

Status

User Prompt

Installed with

Interlock Option

open = On Test position or

Maintenance position, or jumper

removed

Prompts the user to rotate to On Line position,

Just before retransfer.

closed = On “ON LINE” position

(default jumper)

Manual or automatic start (one button) is

allowed all the way to load being On-line

Not installed

open = jumper removed

Prompts the user to install jumper just before

retransfer”

closed = default jumper

Manual or automatic start (one button) is

allowed all the way to load being On-line

Installed without

interlock option

Open = Jumper removed

Prompts the user to install jumper just before

retransfer”

Closed = default jumper

Prompts the user to verify the switch is in on-

line position before a retransfer is allowed

NUMBER OF BATTERY CABINETS

MIN MAX

1 6