Mt. Vernon Pellet Stove (AE)

R

R

F. Convection Blower Replacement

Figure 40.1

Figure 40.3

Depress Tab and

Snap Out Power

Supply

Remove

Left Side

Panel

Disconnect Wire Harness

from Bottom of Blower

Remove 2

Screws

Remove

Right Side

Panel

Figure 40.2

1. Follow the proper shut down procedures as outlined on

page 33, Section 10.A.

2.

Remove the left and right side panels by removing the 

screws using a Phillips head screw driver. Figure 40.1.

. Depress the tab on the left side and snap out the power

supply. You do not need to disconnect any wires.
Figure 40.1.

4.

Remove the  screws at the bottom of the back panel so

there will be room to remove the blower. Figure 40.1

5.

Reach behind the blower and release the latch by push-

ing the top of the latch towards the blower. Figure 40.2.

6. Rock the top of the blower slightly and lift up. The

blower will pass around the control board and out the

left side of the appliance.

7. Disconnect the wire harness from the bottom of the

blower by depressing the tabs on the sides of the con-

nector and then pulling to remove. Figure 40.1.

8. Re-connect wire harness to the new blower.
9. Install replacement blower by placing the bottom flange

into the opening first then rotate blower up into posi-

tion.

10.

When the blower is properly positioned the latch will engage

the notch to hold the blower in place. Figure 36.3.

11. Re-secure the back panel, snap the power supply back

in and re-secure the side panel(s).

Notch