VEGA VEGADIF 65 Foundation Fieldbus User Manual

Page 64

Advertising
background image

64

8 Setup

VEGADIF 65 • Foundation Fieldbus

36130-EN-130417

A

B

+

1

5

6

7

+

2

4

3

II

I

III

III

Fig. 57: Preferred measurement setup for liquids
I VEGADIF 65

II 3-fold valve block

III Separator

1.5 Drain valves

2.4 Inlet valves

3 Breather valve

6, 7 Vent valves on VEGADIF 65

A, B Blocking valves

Proceed as follows:
1. Close valve 3
2. Fill measuring system with medium.

Open valves A, B, 2, 4: Medium flows in.
If necessary, clean the differential pressure lines: - with gases by

blowing out with compressed air - with liquids by rinsing.

5)

Close valve 2 and 4, block the instrument
Open valve 1 and 5
Close valve 1 and 5

3. Remove air from instrument:

Open valves 2 and 4: Medium flows in
Close valve 4: Minus side is closed
Open valve 3: Equalisation plus and minus side
Briefly open valve 6 and 7, then close again: Fill the measuring

instrument completely with the medium and remove air

4. Put measurement loop into operation:

Close valve 3: Separate plus and minus side
Open valve 4: Connect minus side
Now:
Valves 1, 3, 5, 6 and 7 are closed

6)

Measurement setup for

liquids

Prepare the adjustment

5)

Arrangement with 5 valves.

6)

Valves 1, 3, 5: Configuration with 5 valves.