EntelliGuard® G Circuit Breaker

DEH-41304C

Section 3 – Lifting, Mounting and Installation

13 March 14

14

©2012 General Electric All Rights Reserved

Figure 3.7. Circuit Breaker Lifting

3. Remove any padlocks and keep the key in place for key

locks if applied from the racking panel of the cassette.

4. Ensure the cassette position indicator shows

DISCONNECTED and the racking handle is disengaged.

5. Ensure the cassette racking cams on both side walls of

the cassette are in the completely racked out position

as shown in Fig. 3.8.


Figure 3.8. Racking Drive in the DISCONNECTED Position

6. Pull out the cassette rails until they drop into the

horizontal locked position.

7. Lower the circuit breaker gradually so that the rollers

drop over the rails. Ensure the grooves in all rollers

straddle the rails as shown in Fig. 3.9.


Figure 3.9. Circuit Breaker Rollers Straddled on the
Loading Rails

8. Using the hand grips on either side, remove the lifting

bar and push the circuit breaker into the cassette until

it reaches a positive stop (the rollers on circuit breaker

are engaged with the racking cams of the cassette on

both sides). The circuit breaker is now in the

DISCONNECTED position (Fig. 3.10).

Figure 3.10. Circuit Breaker in Disconnected Position.


9. Push back both the extended rails of the cassette to the

stowed position.

10. If the circuit breaker is ON and the springs are charged,

press the OFF button on the circuit breaker fascia and
ensure the circuit breaker contacts are open (Fig. 3.11).

Figure 3.11. Setting the Circuit Breaker to OFF

11. Remove the racking tool from the storage location on

the cassette front panel by grabbing the handle (Fig.
3.12).


Figure 3.12. Racking Handle Storage Location


12. Pull out the torque bar from inside the handle and

extend (Fig. 3.13).


Figure 3.13. Racking Handle Extended