5. Use an M8 nylock nut to mount the motor switch

actuator onto the shaft end, torque to 14.5 N m.

6. Connect the motor connector on to the motor harness.
7. Connect the remaining ground wire from the filter to

the grounding point on the rear of the motor body.


Reverse the above procedure to remove the motorized
spring charging unit

SHUNT TRIP, CLOSING COIL AND UNDER VOLTAGE
RELEASE DEVICE INSTALLATION

NOTICE

The mounting positions of the four devices can be
arranged in the locations as specified in Figure 7.4.


Figure 7.4. Device Location

Combi-
nation

Coil Position on Fascia

1

Network

(IEC)

Interlock

(IEC)

closing coil

under

voltage

2

shunt

shunt

closing coil

under

voltage

3

shunt

UV

closing coil

under

voltage

4

network

under

voltage

closing coil

shunt


Closing Coil Installation (Fig. 7.5)
1. Tilt the device forward and engage the front hooks into

the top support plate.

2. Tilt the device backwards until the rear hooks engage

in the slots

3. Press down into position.

Figure 7.5. Closing Coil Installation

Connect the wire plugs (Fig. 7.6) according to the wiring
schematic in Section 3.

Figure 7.6. Wiring


Closing Coil Removal
1. Disconnect the device and tilt it forward until the rear

hooks disengage.

2. Lift to release the front hooks.

NETWORK INTERLOCK INSTALLATION
When the network interlock is used with the EntelliGuard G,
it will use the C and D positions of the coils as shown in Fig.
7.4. The mounting procedure is same as the coils.

Trip Alarm/Bell Alarm Switch Installation
1. Remove the 40 pin harness (if installed) from the trip unit.
2. Remove the trip unit from the PMU base.
3. Assemble the trip alarm assembly as shown using four

screws.

4. Reassemble the trip unit back on to the PMU base
5. Install the connector from the trip alarm in the specified

location of the SD.

6. Reassemble the 40 pin harness.

Ready to Close Switch Installation
1. Slide the RTC switch assembly on to the mechanism side

sheet.

2. Assemble the screw and washer.
3. Assemble the snap-on connector to make the electrical

connection.

4. Using the cable tie, tie the wires to the PMU base.

SHUTTER PROP OPEN FEATURE

This feature allows the main fixed contacts to be inspected.

DANGER

ELECTROCUTION
Ensure the fixed contacts on the incoming side are isolated
prior to installing the Shutter Prop Open Feature.
Failure to comply with these instructions will result in
death or serious injury.