Commissioning the switchgear

Installing and starting up the switchgear is an important event for the System Administrator. The
following steps must be followed when commissioning the switchgear.

Step 1: Reset Passwords.
See

User administration on page 13

.

Step 2: Set User Settings.
See DEH-501 Entellisys Low Voltage Switchgear System User Manual.

Step 3: Set Local HMI flags.
See

HMI Roles on page 19

.

Step 4: Set System Time Synchronization.
See

Time synchronization on page 33

.

Step 5: Configure System for Remote Communications.
See

Establishing communication to Remote HMIs on page 41

.