3.4 PLACE

OF

INSTALLATION


The UPS should be installed in a restricted area where only qualified personnel should be admitted.

The place of installation should be clean, dust-free, and provided with proper ventilation or air-
conditioning
.

Verify for sufficient floor load capacity (see Section 3.1.1).

We strongly advice that the ambient temperature should not exceed 68° ÷ 77°F / 20° ÷ 25°C (max. 95°F
/ 35°C). See Section 3.5.

Positioning of the UPS LP 33 Series / 50 and 60 kVA

Fig. 3.4-1 Positioning LP 33 Series / 50 & 60 kVA

The rear panel of the UPS may be
mounted flush to a wall or other
structure.

Clearance around the front of the unit
should be sufficient to enable free
passage of personnel with the doors fully
open, and to allow sufficient airflow to the
door vents.

To guarantee proper cooling air exhaust,
the recommended minimum clearance
between ceiling and top of the UPS is 16”
(400mm).

In case of additional cabinets (external
batteries), this must be placed beside the
left side of the UPS cabinet.

A single-phase power outlet (208 VAC)
should be provided near the UPS for
connection of power tools, test
equipment or connectivity devices.
This outlet must be grounded.



The LP 33 Series UPS can radiate radio frequency energy.
Although some RFI (Radio Frequency Interference) filtering is inherent to the UPS there is no guarantee
that the UPS will not influence sensitive devices such as cameras and monitors that are positioned close
by.
If interference is expected, the UPS should be moved away from the sensitive equipment.

NOTE !

Operating temperature is very important for valve regulated battery (maintenance
free).

Operation at temperatures higher than 68°F (20°C) will reduce life expectancy.

Respect the prescription of the battery supplier and other local standards.

The installation and cabling of the battery must be done by qualified people.

Advertising