Installation Guide LP 33 Series 50-60 kVA

3.9.3 Battery

connection


Before proceeding to an external battery connection, follow the Safety rules concerning the battery.
Make sure that the UPS is not powered and remove the external battery protections.

NOTE !

To meet standards concerning electromagnetic compliance, the connection between
the UPS and external Battery
must be done by using a shielded cable or suitable
shielded (metal) conduit!

List of possible battery configurations on LP 33 Series

Autonomy (min.)

Battery cabinet

Battery type

Block number

50 kVA

60 kVA

Note

1 Battery cabinet

33 Ah – 12 V

48

9

8

See Fig. 3.9.3-1

2 Battery cabinets

50 Ah – 12 V

48

(24+24)

16

13

See Fig. 3.9.3-1

2 Battery cabinets

33 Ah – 12 V

96

(48+48)

24

18

See Fig. 3.9.3-1

3 Battery cabinets

50 Ah – 12 V

72

(24+24+24)

29

23

See Fig. 3.9.3-2

4 Battery cabinets

50 Ah – 12 V

96

(24+24+24+24)

39

33

See Fig. 3.9.3-2

UPS with battery cabinet

X4 Battery - Battery connection

-

= Negative pole of the battery

0

= Central point of battery blocks

+ = Positive pole of the battery

GND= Battery cabinet ground

(refer Fig. 3.9.2-2)

Fig. 3.9.3-1 Diagram battery connection

Note !

The UPS unit is supplied with the battery connected as above showed on Fig. 3.9.3-1.