Installation Guide LP 33 Series 50-60 kVA

Output signals on voltage-free contacts

On terminals X1 or J2connector 6 of the following 28 signals can be selected from the display
(access only with password): MENU / PARAMETER MENU / LEVEL 2: SERVICE.

0 - No signal

15 - Battery discharge

1 - Buzzer

16 - Manual bypass ON

2 - General alarm (NO)

17 - Rectifier ON

3 - Load on utility

18 - Inverter ON

4 - Stop operation

19 - Battery boostcharge

5 - Load on inverter

20 - Battery earth fault

6 - Utility failure

21 - Battery fault

7 - DC overvoltage

22 - Relay input 1

8 - Low battery

23 - Relay input 2

9 - Overload

24 - Relay output ON

10 - Overtemperature

25 - Relay output OFF

11 - Inverter utility not syncrony

26 - EPO (Emergency Power Off)

12 - Bypass locked

27 - ECO Mode ON

13 - Bypass utility failure

28 - General alarm (NC)

14 - Rectifier utility failure

Programmable functions on input contacts (X1 - J2)

Some UPS functions can be activated by parameters (access with password only) when an external
NO contact is closed on:

No function

Inverter On

Inverter OFF

Generator ON

Print all

Status relay

External bypass ON

External battery fuses


Voltage free contacts:

Max. DC / AC: 24V / 1.25A
IEC 60950 (SELV circuit)
Min. signal level: 5VDC / 5mA



Gen Set signaling

If an Emergency generator set supplies the UPS in case of utility failure and the generator is particularly
unstable in frequency, it should be suitable to install the signal “generator on” on terminals X1 / 11, 22
(Normally Open voltage-free contact) or on connector J2 / 11, 24 (see Fig. 4.4-1 / X1 and J2).
Since the Parameter for of the reading of the Generator function is password protected, call the nearest
Service Center for it's activation.

When this contact closes, it causes the change of certain settable functions such as:

x Enabling or disabling of synchronization and consequently the load transfer to generator.

x The battery recharge inhibition during the generator operation, or after what delay from generator

start the battery will start to be recharged.


Consult your nearest Service Center for more information.