How to access the terminals for the cable connections

Fig. 3.8.1-1 Access to the input / output connections

To access input, output and battery
connections proceed as follows:

x Open the front door “A” of the cabinet.

x Remove the protection panel “B”.

x Remove the plate “C” for bottom cable

entry.

NOTE !

Drill in the plate “C” appropriate holes for cable conduits (max. 4 x 2 1/2”).
Please remove the plate “C” before drilling any wholes.
See Fig 3.8.1-1
- details “C & D”.



3.8.2

Internal fuse ratings

LP 33 Series internal fuses

The Battery cabinet is equipped
with Breaker FTM3.

In case of replacement the same
type and the same rating must be
used.

Fig. 3.8.2-1 Battery Breaker – FTM3

WARNING !

Wrong polarity
connection can cause
hazard to UPS and
personal. The
replacement of
battery breaker

must be performed
by QUALIFIED
SERVICE PERSONNEL
only.