2 internal fuse ratings – GE Industrial Solutions LP 33 Series 50 & 60 kVA Installation Guide User Manual
Page 28
Modifications reserved
Page 28/42
OPM_LPS_3UI_50K_60K_0US_V010.doc
Installation Guide LP 33 Series 50-60 kVA
How to access the terminals for the cable connections
Fig. 3.8.1-1 Access to the input / output connections
To access input, output and battery
connections proceed as follows:
x Open the front door “A” of the cabinet.
x Remove the protection panel “B”.
x Remove the plate “C” for bottom cable
entry.
NOTE !
Drill in the plate “C” appropriate holes for cable conduits (max. 4 x 2 1/2”).
Please remove the plate “C” before drilling any wholes.
See Fig 3.8.1-1 - details “C & D”.
3.8.2
Internal fuse ratings
LP 33 Series internal fuses
The Battery cabinet is equipped
with Breaker FTM3.
In case of replacement the same
type and the same rating must be
used.
Fig. 3.8.2-1 Battery Breaker – FTM3
WARNING !
Wrong polarity
connection can cause
hazard to UPS and
personal. The
replacement of
battery breaker
must be performed
by QUALIFIED
SERVICE PERSONNEL
only.