Fig. 3.9.4-4 Control bus location RPA parallel system


Control bus location RPA parallel system

Place the cables and connect them as indicated in the diagram Fig. 3.9.5-4 following these
procedures:

x

Fix the control bus cables with the appropriate tie-wrapE”.

x

Place the cables between the parallel units in separated protected conduit to avoid they could
be accidentally interrupted.

x

Put in place the front screen B (Fig. 3.9.4-1) paying attention to not damaging the control bus
cables.



It is important to place the units in sequence of their assigned number.

A unit number from P1 to P4, is defined by the setting of parameters and displayed on the control
panel
.
This number is also marked inside and outside the packaging.


The standard length of the control bus cable between two parallel unit is 26 ft / 8 m.