Ac b, Bottom entry cables top entry cables – GE Industrial Solutions SG Series 10 – 20 – 30 – 40 kVA Installation Guide User Manual
Page 25
Advertising
SG Series 10 & 20 kVA
How to access the terminals for the cable connections.
A
C
B
Bottom entry cables
Top entry cables
SGUL_
010-02
0_UPS
connec
tion_01
US
D
E
!
Please remove the plate "E & F"
before drilling any wholes.
F
Fig. 3.8.1-1 Access to the input / output connections of SG Series 10 & 20 kVA
To access input, output and Battery connections proceed as follows:
• Remove protection panel “A”.
• Remove protection panel “B”.
• Remove UPS side panel “C”.
• Only for Dual Input Utility:
Remove with appropriate tool the metallic window “D” from the metal screen “C”.
Modifications reserved
Page 25/45
OPM_SGS_ISG_10K_40K_0US_V040.doc
Installation Guide SG Series 10 –20 – 30 - 40 kVA
Advertising