G9000 Installation and Operation Manual

49

C)

Bypass Operation Procedure

** Transfer from Inverter to Bypass

1. Check for

“SYNC” on the LCD.

2.

Press the "START/STOP” icon on the LCD.

3. Follow the

“SHUTDOWN GUIDANCE” and Press the "STOP" icon on the LCD.

** Transfer from bypass to inverter.

UPS

1. Press the "START/STOP" icon on the LCD.

2. Follow the

“STARTUP GUIDANCE” and Press the "START" icon on the LCD..


When "REMOTE OPERATION MODE" is displayed on the LCD panel, the

inverter start operation can only be performed remotely. If local inverter start or

stop operation is required (at the UPS), select "LOCAL ONLY" or “REMOTE &

LOCAL” in the OPERATION MENU.

!