CONTROLLING THE SCISSORS LIFT FROM THE PLATFORM.

The control box on the platform is as pictured is adjustable. The controller box
can be hung from any of the collapse rail bars just by tighten or loosening clamp
screw. The pre-conditions, the leveling, and the appropriate selection of the
controls on the front of the main control box are assumed. The three position
selector switch located in front of the main box must be rotated to the left or
platform position. The key may be removed by the operator to ensure the
personnel on the platform retain control of the machine.

The top control button is the emergency stop. To operate the machine this
button must be in the out position.

The next control is a red alarm light. This light is
active at the same time as the alarm horn, which
is located inside the main box.

The next two switches are the up-down and the

push-to-enable buttons. The push-to-enable button
must be pushed to enable the up-down button. These
buttons control the raise/lower functions of the
platform.
To Operate

Climb onto the platform in the back of the lift

Close the drop bar or latch the chain

From the platform push the “push-to-enable

button”, simultaneously while twisting the raise/lower platform button in the desired
direction.