11A. Combined Length of Vent and Combustion Air Duct:



The individual flue vent or the combustion air duct is not to exceed 50 ft in length.



Inputs: 130, 155, 175, and 200 Mbh: 80 feet maximum combined vent & duct



Inputs: 45, 60, 80, 100, and 110 Mbh: 50 feet maximum combined vent & duct



Total combined vent and duct is reduced by ten feet for every 90° elbow installed in the
vent or duct, and in the tube system



Exceeding the allowable lengths noted above may create condensation problems and will
void CSA Design Certification and the heater warranty.

V

ERTICAL

VENT

THROUGH

THE

ROOF

:

It is the sole responsibility of the installer to ad-
here to all current local codes and/or ANSI
Z223.1 / CSA.B149.1 latest editions for all
venting requirements, and practices.



Use an approved ‘B-vent’ termination cap
as supplied by the manufacturer of the ap-
proved ‘B-vent’.



When vent and combustion air are taken
through the roof, the exhaust vent should
always terminate higher than the combus-
tion air intake, to prevent recycling the
products of combustion back into the
heater.

Approved
Cap

Approved
‘B’ Vent

24”

60 cm

12

9

If roof slope exceeds 9:12
consult NFPA-54 ANSI
Z223.1 or CSA-B149.1

12. COMBUSTION AIR DUCTING

An opening is located on the top surface of the burner housing for combustion air . Ensure ade-
quate clearance around this opening to allow sufficient combustion air supply to the heater.
Combustion air duct must be constructed of noncombustible material.

When a tube heater is operated in a negative air condition or air-born dust or contaminants are
present as in woodworking and welding shops, air for combustion must be ducted from outside
the negative or contaminated area to the 4 inch (10 cm) diameter intake flange supplied on the
blower. Maximum vent and duct length is:



The individual flue vent or the combustion air duct is not to exceed 50 ft in length.



Inputs: 130, 155, 175, and 200 Mbh: 80 feet maximum combined vent & duct



Inputs: 45, 60, 80, 100, and 110 Mbh: 50 feet maximum combined vent & duct



Total combined vent and duct is reduced by ten feet for every 90° elbow installed in the
vent or duct and in the tube system.



Exceeding the allowable lengths noted above may create condensation problems and will
void CSA Design Certification and product warranty.