Regency Horizon™ HZ40E-2 Gas Fireplace

INSTALLATION

Diagram 4

Diagram 3: The upper half of the fl ashing is installed
under the roofi ng material and not nailed down
until the chimney is installed. This allows for small

adjustments.

Diagram 2

UNIT INSTALLATION

WITH VERTICAL

TERMINATION

4" X 6-5/8" VENTING

(Rigid Vent Systems)

1) Maintain the 1-1/2" clearances (air spaces) to

combustibles when passing through ceilings,
walls, roofs, enclosures, attic rafter, or other
nearby combustible surfaces. Do not pack
air spaces with insulation.
Check "Venting" Sections for
the maximum vertical rise of the
venting system and the maximum
horizontal offset limitations.

2) Set the gas appliance in its

desired location. Drop a plumb
bob down from the ceiling to the
position of the appliance fl ue
exit, and mark the location where
the vent will penetrate the
ceiling. Drill a small hole
at this point. Next, drop a
plumb bob from the roof to
the hole previously drilled
in the ceiling, and mark the
spot where the vent will penetrate the roof.

3) A Firestop spacer must be installed in the fl oor

or ceiling of every level. To install the Firestop
spacer in a fl at ceiling or wall, cut a 10 inch
square hole. Frame the hole as shown in
Diagram 2 and install the fi restop.

NOTE: For best results and optimum perform-
ance with each approved venting system, it is
highly recommended to apply “Mill-Pac” sealant
(supplied) to every inner pipe connection. Failure
to do so may result in drafting or performance
issues not covered under warranty. Silicone (red
RTV) is optional.

4) Assemble the desired lengths of pipe and

elbows. Ensure that all pipes and elbow con-
nections are in the fully twist-locked position
and sealed.

5) Cut a hole in the roof centered on the small

drilled hole placed in the roof in Step 2. The hole
should be of suffi cient size to meet the minimum
requirements for clearance to combustibles
of 1-1/2". Slip the fl ashing under the shingles
(shingles should overlap half the fl ashing) as
per Diagram 3.

6) Continue to assemble pipe lengths.

Note: If an offset is necessary in the attic to

avoid obstructions, it is important to
support the vent pipe every 3 feet, to
avoid excessive stress on the elbows,
and possible separation. Wall straps
are available for this purpose.


Galvanized pipe is desirable above the roofl ine
due to its higher corrosion resistance. Continue
to add pipe sections through the fl ashing until the
height of the vent cap meets the minimum height
requirements specifi ed in Dia. 4 or local codes.
Note that for steep roof pitches, the vertical
height must be increased. A poor draft, or down
drafting can result from high wind conditions
near big trees or adjoining roof lines, in these
cases, increasing the vent height may solve
the problem.

7) Ensure vent is vertical and secure the base of

the fl ashing to the roof with roofi ng rails, slide
storm collar over the pipe section and seal with
a mastic.

8) Install the vertical termination cap by twist-

locking it.

Note: Any closets or storage spaces, which the

vent passes through must be enclosed.

Diagram 1

Note: All vertical terminations are vented
using 4" x 6-5/8" venting and rigid pipe
adaptor #510-994.

Roof Pitch

Minimum Vent Height

Feet Meters

fl at to 7/12

2

0.61

over 7/12 to 8/12

2

0.61

over 8/12 to 9/12

2

0.61

over 9/12 to 10/12

2.5

0.76

over 10/12 to 11/12

3.25

0.99

over 11/12 to 12/12

4

1.22

over 12/12 to 14/12

5

1.52

over 14/12 to 16/12

6

1.83

over 16/12 to 18/12

7

2.13

over 18/12 to 20/12

7.5

2.29

over 20/12 to 21/12

8

2.44