6. Checkout Procedures

To prepare the System for this checkout:
1. Examine the guarded machine to verify that it is of a type and

design compatible with the EZ-SCREEN. See Section 1.2 for

a list of misapplications.

2. Verify that the EZ-SCREEN is configured for the intended

application (see Section 4.2).

3. Verify that the minimum separation distance from the closest

danger point of the guarded machine to the defined area is

not less than the calculated distance, per Section 3.1.1 of this

manual.

4. Verify that:

Access to any dangerous parts of the guarded machine

is not possible from any direction not protected by the

EZ-SCREEN, hard guarding, or supplemental safeguarding,

and

It is not possible for a person to stand between the defined

area and the dangerous parts of the machine, or

Supplemental safeguarding and hard guarding, as

described by the appropriate safety standards, are in place

and functioning properly in any space (between the defined

area and any hazard) which is large enough to allow a

person to stand undetected by the EZ-SCREEN (see

Sections 3.1.2 and 3.1.4).

5. Verify that all reset switches are mounted outside and in full

view of the guarded area, out of reach of anyone inside the

guarded area, and that means of preventing inadvertent use

is in place (see Section 3.1.3).

6. Examine the electrical wiring connections between the

EZ-SCREEN FSD outputs and the guarded machine’s control

elements to verify that the wiring meets the requirements

stated in Section 3.5.

7. Inspect the area near the defined area (including work

pieces and the guarded machine) for reflective surfaces (see

Section 3.1.6). Remove the reflective surfaces if possible

by relocating them, painting, masking or roughening them.

Remaining problem reflections will become apparent during

the Trip Test in step 11.

8. Apply power to the EZ-SCREEN System. Verify that power to

the guarded machine is OFF. Remove all obstructions from

the defined area. If the EZ-SCREEN is configured for Manual

Power-Up, the Yellow Status indicator will be double-flashing.

Perform a manual reset (close the reset switch for 1/4 to 2

seconds, then open the switch).

Study each procedure in its entirety, to understand each step

thoroughly before beginning. Refer all questions to the Banner

applications engineering department at the address or numbers

listed on the cover of this manual. Checkouts must be performed

as detailed in Section 6.1 below and results should be recorded

and kept in the appropriate place (e.g., near the machine, and/or

in a technical file).

6.1 Schedule of Checkouts

Trip Test: The procedure for EZ-SCREEN trip test is described

in Section 3.4.4. This procedure must be performed at

installation, and at any time the EZ-SCREEN, the guarded

machine, or any part of the application is installed or altered. The

procedure must be performed by a Qualified Person.
Commissioning Checkout: The procedure described in Section

6.2 must be performed at installation or whenever changes

are made to the System (either a new configuration of the

EZ-SCREEN or changes to the machine). The procedure must

be performed by a Qualified Person.
Shift/Daily Checkout: The procedure for “daily” checkout of the

EZ-SCREEN is described on the supplied Daily Checkout card

(Banner p/n 113361 for SLS.. models, P/N 118173 for SLSC..

models). Daily Checkout is to be performed at each shift change

or machine setup change, whenever the System is powered up

— at least daily. The procedure is listed on the Daily Checkout

card and may be performed by a Designated Person or a

Qualified Person.
Semi-Annual Checkout: The procedure for initial checkout of

the EZ-SCREEN System is to be performed every six months,

following installation. The procedure is listed on the Semi-Annual

Checkout card (Banner P/N 113362) and must be performed by

a Qualified Person.

6.2 Commissioning Checkout

Perform this checkout procedure as part of the EZ-SCREEN

installation (after it has been interfaced to the guarded

machine as described in Section 3.5), or whenever changes

are made to the System (either a new configuration of the

EZ-SCREEN or changes to the machine). A Qualified Person

(as defined in Section 4.1) must perform the procedure; checkout

results should be recorded and kept on or near the guarded

machine as required by applicable standards.