INSTALLER'S FINAL CHECK-OUT PROCEDURE

Step 1 Verify that the water pressure is correct for the application. The

water pressure of the Comfort Plus Commercial Hydronic heating

system should be between 12 and 20 psig.

Step 2 Verify that the operating mode displayed on the

control panel corresponds with the power

company's peak control signal. Refer to the

Operating Status section (Page 1.02) for more information on the

proper operating mode.

Step 3 Press the up arrow one time and verify that the

outdoor temperature information displayed on

the control panel is approximately the same as

the current outdoor temperature. Refer to the Operating Status

section (Page 1.02) for more information on the outdoor temperature

display.

HAZARDOUS VOLTAGE:

Risk of electric shock.

Can cause injury or

death. System may be

connected to more than

one branch circuit.

Disconnect power to all

circuits before servicing.

Equipment must be

serviced by a qualified

technician.

WARNING

Step 4 Press the up arrow again and the current heat call status will be displayed on the

control panel. Refer to the Operating Status section (Page 1.02) for more infor-

mation on the heat call status display.

Step 5 Initiate a heat call from the room thermostat and verify that the Comfort Plus Commercial Hydronic

system recognizes the appropriate heat call. Refer to the Operating Status section (Page 1.02) for

information on the various heat call status displays. In applications utilizing the Air Handler, verify

that the Air Handler and/or heat pump operates appropriately.

Step 6 If utilizing the Air Handler, initiate a cooling call from the room thermostat and verify that the

Comfort Plus Commercial Hydronic system recognizes the “COOL” call. Verify that the Air

Handler, heat pump, and/or air conditioner operates appropriately.

Step 7 Press the up arrow until the targeted brick core charge level is displayed on the

control panel. With the system in an off-peak (charge) mode, initiate the charge

control override. Refer to the Charge Control Override section (Page 1.03) for

instructions on initiating the charge control override. Once initiated, the target level of the Comfort

Plus Commercial Hydronic should be 100 percent, the control panel should display “tL: F”, and all of

the heating elements should be energized.

Step 8 With an amp meter, verify that the amperage of the system is correct for the installation. Refer to

the System Identification Label on the Comfort Plus Commercial Hydronic system for information

regarding the proper amperage.

Step 9 Cancel the charge control override and verify that all elements in the system de-energize. Refer to

the Charge Control Override section (Page 1.03) for instructions on canceling the charge control

override.

Step 10 Verify that all hydronic heating zones are operating as intended.
Step 11 Verify, once again, that the “Operating Mode” displayed on the control panel corresponds with the

power company's peak control signal.

Step 12 In applications utilizing the Steffes Power Line Carrier control system, complete the Installer’s Final

Check-out Procedure in the Owner’s and Installer’s Manual provided with that device.