HI HLPS SERIES LOAD POINT ASSEMBLY

Page 20

FIG. 21: ADJUSTING FOR LEVEL WITH SHIM

STOCK

Step 8.

If you tack welded the top plate to the sup-
port bracket, lift the vessel off the load cell
pins if you can) and finish welding the top
plate to the support bracket. If you cannot,
be sure to shield the entire load cell and
cable from any slag that might drop.
Lower the vessel back onto the sliding
loading pins.

WARNING

UNDER NO CIRCUMSTANCES MUST WELD-
ING CURRENT BE ALLOWED TO PASS
THROUGH THE LOAD SENSOR. TO DO SO
WILL DESTROY THE LOAD SENSOR AND
COULD POSSIBLY CAUSE PERSONAL
INJURY AND/OR PROPERTY DAMAGE.

Step 9.

Pour grout up to the bottom surface of the
base plate and let dry.

CAUTION:

DO NOT ALLOW GROUT TO COME IN CON-
TACT WITH THE ANTI-LIFT OFF DEVICE.
(SEE FIG. 13)