PN# 37026500123 05/15/2009

FIG. 2-2 Finding highest point of travel.

OPENER INSTALLATION

FOR HELP-1.800.354.3643 OR WWW.GENIECOMPANY.COM

2

HEADER AND DOOR

MOUNTING BRACKETS:

1. Finding header bracket mounting location.

• Close garage door.

– Use a pencil and level.

a) Mark center of garage door (one-half overall

width) on the wall with 6" vertical line at top

edge of door.

b) Continue this line on wall above door for

about 12"

(Fig. 2-1, a).

• Raise garage door until

top edge of door

reaches its maximum height

(Fig. 2-2).

• With door at highest point.

– Measure height from top edge of door to floor

(Fig. 2-2).

• Close door again.

• Mark height measurement on wall above door

(Fig. 2-1, c).

– Make your mark across vertical line made earlier.

• Add 2-1/2" to height mark just made on wall. This

is location for header bracket

(Fig. 2-1, d).

NOTE: If header bracket location needs to be

above header for garage door opening, you need

to add a "mounting surface." A 2" x 6" board

securely attached (board and fasteners not

included) to wall studs on either side of your mark

is sufficient (Fig. 2-3).

NOTE: For header bracket and bolts locate Bag 2

from Box 1.
NOTE: The bolts supplied in Bag 2 are designed

to be used on pressure treated lumber.

2. Mounting the header bracket.

• Hold header bracket against wall

(Fig. 2-3).

• Position bracket as shown.

– Place center on vertical line,

– Bottom edge on final height line.

• Mark screw hole locations on wall.

• Drill 3/16" pilot holes at each screw hole mark.

– Fasten header bracket with 2 lag screws

(provided)

(Fig. 2-3).

FIG. 2-1 Final height mark.

Header bracket must be fastened to garage

framing.

Do NOT fasten to drywall, particle

board, plaster or other such materials.

WARNING

2-1/2"

top of door

in closed

position

d) - final

height mark

HIGHEST POINT OF TRAVEL

TRACK

SECTIONAL

DOOR

HEADER

FROM HERE

TO FLOOR

2-1/2"

HIGHEST POINT OF TRAVEL

TRACK

SECTIONAL

DOOR

HEADER

FROM HERE

TO FLOOR

a) - 6" vertical

line

b) - extend

vertical line

c) - door at

highest point

door at highest p

oint

door at highes

t point

final height m

ark

final height

mark

2-1/2"

FIG. 2-3 Header bracket mounting (on header &

above header)

.

Door springs are under high tension. If spring or

its shaft is in the way, measure 2-1/2" above

spring or shaft on the garage door centerline and

mark this height as your location for header

bracket.

Do NOT move door spring!