IMPROVING SYSTEM EFFICIENCY

Air flow direction adjustment

1. To improve the effects of cooling and heating, use the outlet louver appropriately for cooling and heating

operations. When in cooling operation the most efficient louver position will be horizontal and when in heating
operation the optimum louver position is downwards.

Increasing heating effect

1. One method increase the warming effect is to fit an additional means of re-circulating the warmed air from the

upper part of the room :

2. However if the warming effect of the air conditioner is not good owing to the installation position or the structure of

the room, then reset the room temperature regulator as follows to raise the temperature of the room. Adjust
position 1 and 2 on DIP switch SW03 located on the indoor P.C. board, according to the table below :

Options

Test operation

To switch the TEST RUN (COOL) mode, push TEMPORARY button for 10
seconds. (The beeper will make a short beep.)

10

FINAL INSTALLATION CHECKS

Precautions

1. Ensure that the electrical cable used for

power supply and control of the system is
unable to come into contact with either
service valves or piping work which are not
insulated.

Electrical wiring

1. When installation is complete, check that all

power supply and interconnecting wiring has
been appropriately protected.

Refrigerant piping

1. When refrigerant and drain piping have been

completed. Ensure that all pipework is fully
insulated and apply finishing tape to seal the
insulation.

Check and Test Operation

• Pressure of R410A is approx. 1.6 times of that of R22.

If installation work is incompletely finished, a gas leakage
may occur at the cases such as pressure rise during
operation.
Therefore, be sure to test the piping connections for leakage.

• Check the flare nut connections, valve stem cap

connections and service port cap fittings
for gas leak with a leak detector or soap water.

Dip switch SW03

position 1 & 2

Temperature increased

Position 1 : ON

Position 1 : OFF

Position 1 : OFF

Position 2 : OFF

Position 2 : ON

Position 2 : OFF

Factory pre-set

+2°C

+4°C

TEMPORARY button

Valve
cover

Cord clamp

Piping cover

Indoor/outdoor
connecting cables

Power cable

Flare nut
connections
(Indoor unit)