DRAIN PIPING WORK

Piping material

• For laying pipes underground, use hard vinyl

chloride pipe. (Inner diam. 20 or 25mm)

Piping and cautions

• Set drain side of pipe at downward slope.

(1/100 or more)

• Be sure to apply thermal insulation (foaming

polyethylene, 10mm-thickness or more) for pipes
passing through the room.

• Adhere the connecting sections with vinyl chloride

agent surely so that no water leakage is caused.

• Support the piping with hanging bracket so that the

force is not applied to connection sections of pipe
and pipe is not waved.

NOTES :

• Do not make slack or trap at halfway across piping.

• Set pipes so that the end of drain pipe is not dipped in

water, and also keep space 50mm or more to the
ground.

• After piping work, check if water drains smoothly.

• Hole should be made at a slight downward slant to

the outdoor side.

• When connecting extension drain hose, insulate the

connecting part of extension drain hose with shield
pipe.

Trap

Arched shape

Support
bracket

1/100 or more
downward slope

Thermal
insulator

Indoor
unit

1.5m to 2m

50 mm
or more

Do not put the drain hose
end into water or drainage.

Shield pipe (local parts)

Extension drain hose

Inside the room

Drain hose

As long as possible (Approx. 100mm)

VP 30 or more

Downward grading
1/100 or more

VP 30

VP 30

VP 30

Extended
ventilating pipe

• As shown in the figure, set the collective piping such

as the ceiling duct so that waste water does not back
up from the main pipe.

Connection of the drain hose

• Insert the drain hose completely into the connecting port of the drain pan.

• Apply thermal insulation surely to the drain hose with socket thermal insulation seal.