Part number 550-110-260/0508

28

GOLD CGs Gas-Fired Water Boiler — Boiler Manual

Start-up — operate boiler

7b

Inspect system water piping

After fi lling the boiler and system with water,

inspect all

piping

throughout the system for leaks. If found, repair

immediately. Repeat this inspection after the boiler has
been started and the system has heated up.

Leaks must be repaired at once.

Failure to do so can damage the
boiler, resulting in substantial prop-
erty damage.

Do not use

petroleum-based

cleaning or sealing compounds

in boiler system. Severe damage to
boiler will occur, resulting in sub-
stantial property damage.

Start-up — preparation

(continued)

7a

Final check before starting
boiler

• Read manual Section

9

including the

Operating

instructions

(Section

9c

).

Verify the boiler and system are

full of water

.

• Verify

the

Start-up preparation

procedures of Sec-

tion

7a

have been completed.

Start the boiler

• Follow

the

Operating instructions

from Section

9c

to start the boiler.

• See

Section

7c

if boiler fails to start.

Check system and boiler

Do not use

petroleum-based

cleaning or sealing compounds

in boiler system. Severe damage to
boiler will occur, resulting in sub-
stantial property damage.

Eliminate all system leaks

. Continual fresh makeup

water will reduce boiler life. Minerals can build up in
sections, reducing heat transfer, overheating cast iron,
and causing section failure.

1.

Check system piping for leaks

. If found, shut down boiler and repair

immediately.

2.

Vent air from system

using manual vents. Air in the system will interfere

with circulation and cause heat distribution problems and noise.

3.

Inspect vent system

thoroughly for signs of deterioration from cor-

rosion, physical damage or sagging. In addition — Check for gas-tight
seal at every connection and seam.

Venting system must be sealed gas-tight

to prevent

fl ue gas spillage and carbon monoxide emissions which
will result in severe personal injury or death.

4.

Check around the boiler

for gas odor following the procedure of Sec-

tion

7a

of this manual.

5.

Verify operation

per Section

7b

. Perform check-out procedure in Sec-

tion

8

, and fi ll in the

Installation and service certifi cate

on the same

page.

Inspect base insulation

Check to make sure

insulation is secure

against all

four sides of the base. If insulation is damaged or dis-
placed,

do not

operate boiler. Replace or reposition

insulation.

Failure to replace

damaged insu-

lation or reposition insulation can
result in a fi re hazard, causing severe
personal injury, death or substantial
property damage.

The boiler contains ceramic fi ber
and fi berglass materials. Use care
when handling these materials per
instructions on

page 64

of this

manual. Failure to comply could
result in severe personal injury.