Check-out procedure — checklist

8

❏ Boiler and heat distribution units fi lled with water?
❏ Automatic air vent, if used, open one full turn?
❏ Air purged from system?
❏ Air purged from gas piping? Piping checked for leaks?
❏ Correctly sized manifold orifi ces installed? Refer to manual

Section

2a

to check size and fuel type.

Correctly sized manifold orifi ces must be used.
Failure to do so will cause severe personal in-
jury, death or substantial property damage.

❏ Followed operating instructions on boiler or in manual

Section

9

for proper start-up?

❏ Proper burner fl ame observed? Refer to

Check burner

fl ame

, manual Section

7b

.

❏ Test limit control — While burners are operating, move

indicator on limit control below actual boiler water tem-
perature. Burners should go off while circulator continues
to operate. Raise setting on limit control above boiler water
temperature and burners should reignite.

❏ Test additional fi eld-installed controls — If boiler has a low

water cutoff, additional high limit or other controls, test for
operation as outlined by manufacturer. Burners should be
operating and should go off when controls are tested. When
controls are restored, burners should reignite.

❏ Test ignition system safety device:

a. Connect manometer to outlet side of gas valve.
b. Start boiler, allowing for normal start-up cycle to oc-

cur and main burners to ignite.

c. With main burners on, manually shut off gas supply

at manual main shutoff gas valve. Burners should go
off.

d. Open manual main shutoff gas valve. Manometer

should confi rm there is no gas fl ow.

e. Pilot will relight, fl ame sensing element will sense

pilot fl ame and main burners will reignite.

❏ Set limit control(s) to system temperature requirements.

Adjust balancing valves and controls to provide design
temperature to system.

❏ For multiple zones, adjust fl ow so it is about the same in

each zone.

❏ Verify thermostat heat anticipator (if available) set properly?

Refer to

Field wiring

, manual Section

6

,

Thermostat(s)

.

❏ Cycle boiler with thermostat — Raise to highest setting and

verify boiler goes through normal start-up cycle. Lower to
lowest setting and verify boiler goes off.

❏ Measure natural gas input:

a. Operate boiler 10 minutes.
b. Turn off other appliances.
c. At natural gas meter, measure time (in seconds) re-

quired to use one cubic foot of gas.

d. Calculate gas input:

3600 x 1000

number of seconds from step c

= Btuh

e. Btuh calculated should approximate input rating on

boiler rating label.

❏ Check manifold gas pressure by connecting manometer to

downstream test tapping on main gas valve. Manifold pres-
sure for natural gas should be 3.5" w.c. and for propane gas
should be 10" w.c.

❏ Observe several operating cycles for proper operation.
❏ Set room thermostat to desired room temperature.
❏ Fill in Installation and service certifi cate below?
❏ Review all instructions shipped with this boiler with owner

or maintenance person. Return instructions to envelope
and give to owner or place in pocket inside front panel in
boiler.

Installation and service certifi cate

Boiler model __________________ Series __________ CP number ___________ Date installed ___________

Measured Btuh input ____________________

Installer ________________________ ________________________________ ________________________
(company) (address) (phone)

Installer’s signature: _____________________________________

❏ Installation instructions have been followed.

❏ Check out sequence has been performed.

❏ Above information is certifi ed to be correct.

❏ Information received and left with owner/maintenance person