8. Installation

PNEG-1276 Top Dry Autoflow Construction Manual 24', 30' and 36'

39

36' Intermediate Purlin

The upper purlins are bolted using 5/16" x 1-1/4" bolts in the ninth hole counting up from the sidewall. The
middle purlins are bolted in the fourth hole counting up from the sidewall. Bolt purlins to rafters with interior
angle facing the center of the bin as shown in

Figure 8E

.

Figure 8E

The angle is to be bolted on the underneath side of the
rafters, joining rafter to rafter, with the angles interior
angle facing the center of the bin.