36' leveling band post installation, Leveling band installation – Grain Systems PNEG-1276 User Manual

Page 46

Advertising
background image

8. Installation

46

PNEG-1276 Top Dry Autoflow Construction Manual 24', 30' and 36'

36' Leveling Band Post Installation

Install the leveling band posts on the floor as shown in

Figure 8O

.

The third, sixth, tenth and twelfth holes in the floor sheets indicate the location of the leveling band posts.
Attach with 5/16" x 1-1/4" bin bolts (S-277). In the third hole from the bottom of the floor sheets there will
be eighteen (18) posts (one in every other sheet). In the sixth and tenth hole there will be twelve (12) posts
(1 at every third sheet). In the twelfth hole there will be six (6) posts (1 every sixth sheet).

Figure 8O

Leveling Band Installation

NOTE: Field cut rounded notches in the outer leveling band(s) where the two (2) roof support channels

hang from the roof ribs.

(See Figure 8P.)

Figure 8P