Wiring – Controlled Products Systems Group CSL24VH User Manual

Page 21

Advertising
background image

19

DUAL GATES ONLY + CONNECT BATTERIES

WIRING

DUAL GATES ONLY

BIPART DELAY/SYNCHRONIZED CLOSE

The LOCK/BIPART DELAY switch is used only with dual gate applications and

serves two functions:
BIPART DELAY
SWING GATE APPLICATIONS: The BIPART DELAY is used in applications

where a mag-lock, solenoid lock, or decorative overlay would require one

gate to close before the other. The operator with the LOCK/BIPART DELAY

switch ON will delay from the close limit when opening and be the first to

close from the open limit.

SLIDE GATE APPLICATIONS: Not applicable, set to OFF.

SYNCHRONIZED CLOSE
The BIPART DELAY is also used in applications where one gate travels a

longer distance than the other. To synchronize the closing of the gates, set

the LOCK/BIPART DELAY switch to ON for both operators.

+

+

-

-

J15 Plug

Jumper

Black Wire

Red Wire

The batteries are charged in the circuit by the integrated transformer. The batteries

are for battery backup or solar installation.

1

Turn OFF AC power to the operator.

2

Unplug the J15 plug labeled BATT on the control board by squeezing the plug

and pulling it from the control board.

3

Connect a jumper between the positive (+) terminal of one battery to the

negative terminal (-) of the other battery.

4

Connect the red wire from the J15 plug to the positive (+) terminal of the

battery.

5

Connect the black wire from the J15 plug to the negative (-) terminal of the

battery.

6

Plug the J15 plug back into the control board. This will power up the control

board.

7

Turn ON AC power to the operator.

8

Turn ON the AC power switch on the operator.

ALARM

RESET

7AH BATTERIES

CONNECT BATTERIES

(with heater)

(without heater)

Advertising