8 MAINTENANCE
NOTE
The operations outlined in this chapter are to be
performed by qualified maintenance personnel only.
8.1 Maintenance Schedule
Table 8-1: Preventative Maintenance Schedule
Item
Maintenance Interval
Reference Section
TEST functions
Check every month
Zero/Span Calibration
Weekly or as needed
Zero/Span checks
Daily
Particulate Filter
Weekly as needed
Zero air canister
Refill every 3 months
Zero Air DFU filter
Change every 12 months
Reaction cell cleaning
Clean annually and clean as necessary
Sample Flow
Check every 6 months
Pneumatic Lines
Examine every 12 months, clean if
necessary
Factory Calibration
Calibrate each year or after repairs
Leak Check
Check every year
Pump Diaphragm
Change annually