Commissioning Procedure

PRE COMMISSIONING CHECKLIST

Adjust the water temperature supply and return set points (if necessary) to call for 100%
cooling (refer to

Controls

, on page 39).

Ensure all KNOBS and SWITCHES are adjusted to suit the design requirements
(refer to

Controls

, on page 39)

To switch the unit ON, use the microprocessor keypad as follows:

Press

Prg

, press

, press

, press

& finally

CAUTION

There will always be a delay between the enabling of the unit and the energising of
the compressor contactors, anything between 1 to 2 minutes. Be patient.

Check that there is a 2 seconds delay between the Star and Delta contactor energising on
each circuit.

CAUTION

This delay period would be 0.7 seconds in Closed Transition Starting.

Check capacity control timing as detailed previously

Check that each circuit trips on low pressure, the alarm should appear within
3 minutes

The alarm will be recognised at the display circuit trip, to clear the alarms refer to

Alarm Handling

, on page 42

CAUTION

Prior to the chiller compressors being allowed to start, the Water Flow Fail and
Pump Interlock features MUST both be proven to work correctly.

To check the water flow fail safety protection is working satisfactorily:

RECORD

Reduce the flow rate to 75% of design and ensure that the evaporator pressure or
flow protection switch trips at this flow rate, adjust as necessary

With compressors off, ensure this alarm is recognised as “Water Flow Fail” at the
display and disengages the circuits operation immediately, restore flow rate to the
design and check the alarm has self-cleared

To check the pump interlock safety feature works satisfactorily:

RECORD

Switch off the chiller water pump and check the interlock wiring connections at the
chiller are open circuit

To switch the unit OFF, use the microprocessor keypad as follows:

Press

Prg

, press

, press

, press

& finally

Fully open all liquid line and discharge service ball valves on each circuit

CAUTION

Re-instate both the liquid injection and liquid line solenoid valves.

Remove the link from the MCCB for the auxiliary alarm contact.

Fully open all liquid line and discharge service ball valves on each circuit.