Use the sling-rigged method to lift large detectors into a vertical position while they are still crated . Use this method

to position while they are still crated . Use this method to position large detectors vertically into pipelines .

Figure 3: Sling-Rigged Lifting Methods

Do not lift a detector with a forklift by positioning the detector body on the forks, with the flanges extending beyond

the lift . This could dent the housing or damage the internal coil assemblies .

Never place forklift forks, rigging chains, straps, slings, hooks or other lifting devices inside or through the detector's

flow tube to hoist the unit . This could damage the isolating liner .

Do not lift detector with forklift .

Do not lift or rig lifting devices through detector .

Figure 4: Lifting and Rigging Cautions