1 base foundation, 1 supplied components, 2 installation – Campbell Scientific T.Weather T107 Toro Weather Station User Manual

Page 19: Base foundation, Supplied components, Installation

Advertising
background image

T107 Weather Station

User supplies valve box at base of station and weatherproof

enclosure for transformer. See FIGURE 2-1.

The AC power supply option at one time included a step-down

transformer instead of the power supply. Appendix E provides

information about using the step-down transformer.

2.1 Base Foundation

2.1.1 Supplied Components

(3) 5/8 inch Anchor L-Bolts

(9) 5/8 inch Nuts

(1) Anchor Template

Refer to Section 1, Preparation and Siting, for components supplied by

installer and bring components.

2.1.2 Installation

1. The ET Tower attaches to a user supplied concrete foundation constructed

as shown in FIGURE 2-2.

2. Construct the concrete form with 2 inch x 4 inch lumber and 16p nails.

3. Assemble the template and anchor bolts. There should be two nuts below

and one nut above the template on each bolt.

4. Clear an area large enough to set the form at the desired elevation.

5. Dig a hole 2 feet x 2 feet x 2 feet. Lighter soils may require a deeper hole.

About 20 inches below the top of the hole, gouge a small cavity in one

wall of the hole. The cavity should be about 4 inches deep and just large

enough in diameter to insert one end of the conduit. Make certain the

cavity “points” in the direction from which power and communications

cables will come. For example the cavity will “point” towards a valve box

if one is being used.

6. Center the form over the hole. Adjacent to the form, drive four stakes into

the soil. Secure the leveled form to the stakes with the 8p nails.

7. Cap the ends of the conduit with duct tape. Position the conduit and wire

into place by securing the wire to nails in the form.

8. Fill the hole and form with approximately 1/2 yard of concrete. Screed the

concrete level with the top of the form. Center the template assembly over

the conduit and press into the concrete. Put 2 x 4 spacers between the

template and the top of the form. The bottom of the bolt threads should be

about 1/2 inch above the concrete. The template must be level in two

dimensions. Use a trowel and edger to finish.

9. Wait 24 hours before removing the concrete form. Wait 7 days before

mounting the ET Tower.

NOTE

NOTE

11