7 commissioning, Before switching on, Commissioning 61 – Lenze E82ZAFUC001 User Manual
Page 61
Advertising
Commissioning
Before switching on
7
EDK82ZAFUC−001 DE/EN/FR 4.0
61
l
H1inbet−weitereINB hinweis
7
Commissioning
Before switching on
(
Stop!
Before switching on the standard device with the function module for the first
time, check...
ƒ
the entire wiring with regard to completeness, short circuit, and earth
fault.
ƒ
whether the bus system is terminated by a bus terminating resistor at the
physically first and last node.
)
Note!
A generally applicable description for commissioning function modules with a
CANopen communication profile using one of the numerous programs
available on the market cannot be provided within the scope of this
documentation.
Such a program is not included in Lenze’s scope of supply.
Advertising