Commissioning

Switch−on sequence

7

l

66

EDK10200EV3 DE/EN/FR 7.1

Switch−on sequence

1. Before switching on the supply voltage check the wiring for completeness and short

circuit.

2.

Switch on the supply voltage for the Drive PLC and the PC.

3. Start the Drive PLC Developer Studio" (DDS) software.
4. Set the communication parameters. (

¶ Drive PLC Developer Studio − Getting

started")

5.

Load the required project into the Drive PLC. (

¶ Drive PLC Developer Studio −

Getting started")

6. Start the program. (

¶ Drive PLC Developer Studio − Getting started")

Program control

You have various options to control the program in the Drive PLC:

Control with

Program function

Setting/parameter setting

Software Drive PLC Developer
Studio (DDS)

start, stop, reset

^

DDS Manual − Getting started"

l

Software Global Drive
Control" (GDC)

l

Keypad XT 9371BC

Automatic start

C2104 = −0−

*)

Program does not start
automatically after power−on

C2104 = −1−

Program starts automatically
after power−on

start, stop, reset

C2108 = −0−

*)

Function executed

C2108 = −1−

Start program

C2108 = −2−

Stop program

C2108 = −3−

Reset program

*)

Lenze setting