Step 7, Magna-loc, Installation of panel – Metal Sales Magna-Loc Installation User Manual

Page 51

Advertising
background image

© Metal Sales Manufacturing Corporation / Subject to change without notice 6/12

51

MAGNA-LOC

INSTALLATION OF PANEL (

cont

.)

Note: The following steps are for terminating a panel run when the pan width exceeds the width of

the building.

TERMINATION OF PANEL

Last Full Panel

A

A

INSTALLING

PANEL CLIP

STEP

7

"C" Clamp

Floating Rake Zee

Termination Panel

Last Full Panel

2"

Field bend

simulated Male Leg

90°

2"

A

Steps:

1. When the roof panel installation has reached the opposite end of the roof, the last panel run may need to be field modified

to attach to the Floating Rake Zee previously installed.

2. Measure the distance between the vertical leg of the last full panel run and the vertical leg of the Floating Rake Zee

at the eave, endlap, and peak. See dimension “A”.

3. Determine if a full panel will fit between the last full run and the Floating Rake Zee. In most cases it will not fit. If the

full panel will fit, then continue with the installation of the roof. When the last panel is installed the vertical leg of the

male side must fit flush with the Floating Rake Zee.

4. If a full panel is too wide to fit between the last full panel run and the Floating Rake Zee, a panel will have to be field

cut and bent to simulate a male leg.

5. Use the dimension “A” and mark a line on the last panel to serve as the bend line. Mark a second line 2" past the bend line

to be the line you will cut off the excess panel.

6. Field bend the roof panel up 90 degrees to form a vertical leg.

7. Place termination panel between last full panel and vertical leg of Floating Rake Zee making sure the panel fits properly.

8. Clamp termination panel to leg of Floating Rake Zee until Rake Detail is to be installed. (See page 60 for details.)

Advertising