MAGNA-LOC

peAK wItH eNd dAM OVer deCKING

INstALLAtION NOtes

Magna-Loc Eave Plate and Magna-Loc panels must be installed prior to peak installation (see page 44).

1. Once panels have been installed and properly sealed, (see page 45) apply a row of Double Bead Tape Sealant across panel,

up and over all ribs approximately 2"-4" from panel end.

2. Install Magna-Loc End Dams over Tape Sealant. Before continuing make sure End Dam placement will accommodate

Peak Flashing.

3. Once closure is set in Tape Sealant, fasten through End Dam, Double Bead Tape Sealant, Magna-Loc panel, and into Eave

Plate with (5) #12-14x1" SD N/W per panel.

4. Once all End Dams have been installed, place a row of Double Bead Tape Sealant across top of End Dams. Tube sealant

must be used to fill any and all gaps left around End Dams.

5. Position and install Cleat to wall with appropriate fastener, 12"o.c. Make sure Cleat allows for proper Peak attachment.

6. Install Peak flashing by sliding open hem onto Cleat and resting the Peak flashing back over End Dams. Secure to top leg

of End Dams with ¼"-14 x

7

/

8

" Stitch XL at the spacing shown above.

7. If two or more flashings are required, lap the flashing over the previously installed flashing by a minimum of 2" placing a

bead of Tube Sealant between the flashings and securing with Pop Rivets, 2.5"o.c.

Double Bead Tape Sealant

#10-12" x 1" PHW (1'-0" o.c.)

Cleat

Magna-Loc End Dam

Magna-Loc Panel

1

/

4

"-14 x

7

/

8

" Stitch XL (3 per panel)

Floating Clip W/ (2) #10-12 x 1" PHW

Moisture Barrier (by others)
#10-12 x 1" PHW

#12-14 x 1" SD N/W (see below)

Peak

#12-14 x 1" SD NW

1

3

2

5

4

FASTENING PATTERN

1

/

2

:12 slope

Minimum