Chapter 3: installation & startup, Overview, Mounting the m2 rig monitor – RKI Instruments M2 Rig Monitor User Manual

Page 15

Advertising
background image

M2 Rig Monitor Operator’s Manual

10

Chapter 3: Installation & Startup

Overview

This chapter describes procedures to mount the M2 Rig Monitor in the monitoring
environment and wire it to input power and devices.

Mounting the M2 Rig Monitor

Perform the following procedure to install the instrument housing at the mounting site.

Figure 6: Rig Monitor Outline and Mounting Dimensions

1.

Select a mounting site that is representative of the monitoring environment. Consider
the following when you select the mounting site.

Select a site where the Rig Monitor is not likely to be bumped or disturbed. Make
sure there is sufficient room to perform start-up, maintenance, and calibration
procedures.

Is a DC power source available?

9.62

3.43

1.5 max

6.8 max

2.75

6.89

13.50

6.56

1.1

6.1

Ø . 25 Mouting Holes (2X)

5.46

Advertising