7. Locate the Labx I/O modules in the CEE0101 folder of the Project tab.
8. Load the IOMs by doing the following:
a. Select all of the IOMs in the I/O list area.
b. Click the green down arrow (load) in the toolbar.
The Load dialog box appears.
c. Verify that the I/O modules are all checked and click OK.
The assigned I/O modules appear under their CPM in the Monitoring and Project
tabs.
TIP
To locate the IOMs, you may need to expand the CEE and I/O
branches of the tree in the Project tab.
ATTENTION
!
Load only the I/O modules that physically exist in the chassis.
TIP
In Monitoring tab:
• blue indicates “inactive,”
• green indicates “active and OK.”
• red indicates “active and failed.”
Double-click the I/O module in the Monitoring tab to see connection
status on the Module Configuration tab.