To execute your program, you must change the CEE and CM from inactive to active. Follow
these steps to change the CEE, CM, and IOMs to active:

1. In the Monitoring tab, click CEE0101.

2. Select Operate⇒Activate⇒Selected CEE and its IOMs and CMs and Applicable

Function Blocks.

3. Click Yes to change the state of the selected objects. You see the CEE and everything

listed under it in the tree view under the Monitoring tab go solid green.

Verifying Proper Operation

Follow these steps to verify that your PID loop operates properly:

1. In the Monitoring tab, double-click FIC102. The PID diagram opens.

2. On the PID block, look at the MODE parameter to ensure that it is set to MAN

(manual).

3. With the PID block in manual mode, double-click the OP parameter.

4. Set the OP Value in % to 80.

5. Click Yes when prompted to Change Online value and click OK.

6. On the PID block, double-click the MODE parameter and set it to AUTO

(automatic).

7. Click Yes when prompted to Change Online Value and click OK.

8. Double-click the setpoint wire (SP) and set the setpoint to 25.

9. Click Yes when prompted to Change Online Value and click OK.