Chapter 3, Final checklist before energizing, Perform a pre-energizing check procedure – Rockwell Automation 1748 DataSite Configured Panel Installation Instructions User Manual

Page 23: Chapter

Advertising
background image

23

Publication 1748-IN001B-EN-P - May 2009

Chapter

3

Final Checklist Before Energizing

This chapter provides guidance for the start-up of a newly installed DataSite
configured panel.

It is recommended to make an itemized list including the following
information:

Serial number

Number of units and their locations

System voltage

Other important data.

This itemized list should be saved in a file along with other data for the
installation of the DataSite controller, such as component manuals, radio
manuals, and wiring diagrams.

Perform a Pre-energizing
Check Procedure

The following procedures should be performed by a “qualified person” as
defined by Standards Publication NFPA 70E, 2004, “Standard for Electrical
Safety in the Workplace” Article 110 “Qualified Person”:

“A qualified person shall be trained and knowledgeable of the
construction and operations of equipment or a specific work method
and be trained to recognize and avoid the electrical hazards that might
be presented with respect to that equipment or work method.

a. Such person shall also be familiar with the proper use of the special

precautionary techniques…

b. An employee who is undergoing on-the-job training and who, in the

course of such training, has demonstrated the ability to perform
duties safely at his or her level of training…

c. Such persons permitted to work within the Limited Approach

Boundary of exposed live parts operating at 50 volts or more…”